DOMINION BOULEVARD CORRIDOR STUDY | Chesapeake, Virginia
124 | Infrastructure Strategy
Opportunity Site - Area 10
All costs for Area 10 are based on the following assumptions:
1. Services will connect to the proposed water and sewer infrastructure on the proposed Pleasant Grove Parkway.
2. Only water and sewer costs shown are for projected Program Allocations, not full build-out of Area.
3. If development requires hire flows than typical light industrial, an elevated water storage tank and larger water
main will likely be required.
4. All costs will ultimately be the responsibility of the developer(s)
APPROXIMATE UTILITY COSTS TO SERVE AREA 10
Sewer
Water (Light Industrial)
Elevated Water Storage Tank
$3,000,000
$2,500,000
$3,000,000